Lots 23 - 29

When will my home be ready?

Civil construction

Completed

Home construction

Complete

Estimated home construction completion timeframe

Mid-July 2021

Settlement

Complete

Key documents

Comments

UPDATE - 2nd AUGUST 2021 

Settlement of Cluster 6 lots commenced on 30th July and is currently in progress.


UPDATE - 21st JULY 2021 

You will have received communication recently about both inspection and settlement timeframes for your townhome. As a result of the current lockdown continuing in Victoria to slow the spread of COVID-19, our team will continue to provide updates on revised inspection and settlement timeframes as soon as these are available.


UPDATE - 18th JUNE 2021 

Following our previous communication in early May regarding progress of your Alfie townhome, valuation inspection timeframes have now been confirmed.

Valuation inspections of your townhome can be undertaken by your bank lender during the week commencing Monday 28th June 2021.

If you have not done already, please contact your bank lender to have their nominated valuer arrange an inspection. 

The valuer must contact Ewan Hutchinson (RPM Real Estate) on 0487 888 860 to confirm their requested time to conduct a valuation during the week indicated above. This will ensure appropriate access to the construction site can be facilitated with the builder.

At the time of the valuation inspection, your valuer must observe any COVID-19 health and safety measures that apply to real estate services and inspections, as per directions of the Victorian Chief Health Officer.  For further information, please visit https://www.dhhs.vic.gov.au/coronavirus 

The current estimated pre-settlement inspection and settlement timeframes are listed below:

  • Pre-settlement inspection Mid-July 2021
  • Settlement Late-July 2021

Should these dates be revised further, we will be in contact again to advise of the new timeframes, once these have been confirmed.

Should the valuer require any information relating to your townhome as part of their inspection, or if you have any questions about the valuation inspection and settlement process, please don’t hesitate to contact us via email alfiesettlements@rpmrealestate.com.au 


UPDATE - 6th MAY 2021 

We would like to provide a further update regarding the progress of your Alfie townhome.

Due to some minor delays during the final stages of works on site, we’ve had to make some changes to the previously advised inspection and settlement timeframes.

The latest updates are outlined below:

  • Valuation inspection Late-June 2021
  • Pre-settlement inspection Mid-July  2021
  • Settlement Late-July 2021

We do apologise for the need to revise these timeframes and our team will continue to keep you updated on the progress of your townhome.  We will be in contact again to advise specific inspection and settlement dates, once these have been confirmed.

Should you require any information around the process leading up to settlement of your townhome, please don’t hesitate to contact us via email alfiesettlements@rpmrealestate.com.au 

 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction will commence after civil construction is completed.

Home Construction Progress

home construction commences
100% COMPLETE
home construction complete
slab
Concrete footings for base is poured.
frame
Construction and set-up of frame for approval by a building surveyor.
lock up
External wall cladding and roof covering is completed. External doors and external windows are fixed.
internal
fit out
All internal fittings including architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted or fixed into position. Flooring is laid.
landscaping
Landscaping within your property is completed.
practical
completion
All building work is either complete or close to completion, in accordance with the contract/agreement with the relevant authorities. Property is reasonably fit for occupation.
final inspection
Final visit by building inspectors to ensure all fittings, fixtures are complete, in good condition and built to the standard and specification as indicated in relevant contracts/agreement. Certificate of occupancy is issued.
handover
All works are finalised and ready to hand over to purchaser to move in.