Lots 9-16 - Framing complete, rough-in of internal services commenced - July 2020
Lots 23-29 Framing complete, brickwork commenced - July 2020
Lots 30-36 Brickwork and cladding underway, rough in of internal services commenced - July 2020
Lots 17-22 Framing complete, rough-in and brickwork to follow - July 2020
Lots 1-8 - Brickwork nearing completion, Plaster underway - July 2020
Lots 37-45 - Cladding complete, joinery installed, painting underway - July 2020
Lots 37-45 Plaster & kitchen installation complete, painting & fit-off underway - July 2020
Stage 2 and 3 civil construction - July 2020